This demanding project involved the removal of an old asbestos
roof and the installation of a new robust roof to improve the
safety and wellbeing of pupils and staff. The process has been
transformative for the school, using VELUX Modular Skylights
to create a brighter, fresher space for everyone.
With the asbestos roof located in the centre of the building,
access was extremely complex. There was time pressure too,
as all the work had to take place within the 6-week summer
break, ensuring the school could re-open in time for the
autumn term.
The first stage was the installation of a large temporary
roof over the whole building to ensure the environment
was watertight and safe. The asbestos was carefully removed
and disposed of using the correct methods, which involved
transporting the contaminants up and over external walls
surrounding the asbestos roof. The whole project was
completed four days early due to good management and
the ease and speed of installation of the 100% pre-fabricated
VELUX ridgelights.
In partnership with the school, a time-lapse video was made
of the entire stripping and re-roofing process, and it was given
to the school for educational purposes. View the video at
mjconstructiongroup.co.uk/projects/chessbrook-school